What is the primary purpose of the Managing a Stage Boundary (SB) process in PRINCE2?
-
A
To enable the Project Board to assess project viability and decide whether to authorize the next stage
-
B
To record all issues and changes that occurred during the stage
-
C
To allocate work packages to team managers for the next stage
-
D
To report project progress directly to corporate or programme management