What is the relationship between Checkpoint Reports and Highlight Reports in PRINCE2?
-
A
They are the same document with different names at different management levels
-
B
Information from Checkpoint Reports feeds into the Project Manager's Highlight Reports
-
C
Highlight Reports replace Checkpoint Reports when a stage ends
-
D
They are produced simultaneously by the Project Manager