PMP Procurement Management 3 — Questions and Answers
Question 1: Which procurement document is MOST appropriate when the buyer wants vendors to propose innovative solutions?
- Invitation for Bid (IFB)
- Request for Quotation (RFQ)
- Request for Proposal (RFP) (Correct answer)
- Request for Information (RFI)
Correct answer: Request for Proposal (RFP)
An RFP allows vendors to propose their own approach and solution, making it ideal when innovation and technical approach matter more than just price.
Question 2: A project manager is closing a contract and discovers the vendor met all deliverables but a key stakeholder is dissatisfied. What should the project manager do?
- Reject the deliverables and withhold final payment
- Close the contract since requirements were met, then address satisfaction through lessons learned (Correct answer)
- Extend the contract to allow the vendor to address stakeholder concerns
- Escalate to the sponsor to override the stakeholder's dissatisfaction
Correct answer: Close the contract since requirements were met, then address satisfaction through lessons learned
If contractual obligations were met, the contract should be formally closed; stakeholder satisfaction issues should be documented in lessons learned for future procurements.
Question 3: What distinguishes a Firm Fixed Price (FFP) contract from a Fixed Price with Economic Price Adjustment (FP-EPA)?
- FFP allows for scope changes; FP-EPA does not
- FP-EPA includes pre-defined adjustments for inflation or economic conditions over long contract periods (Correct answer)
- FFP is used for services; FP-EPA is used for goods only
- FP-EPA transfers more risk to the buyer than FFP
Correct answer: FP-EPA includes pre-defined adjustments for inflation or economic conditions over long contract periods
FP-EPA contracts include pre-defined clauses that allow price adjustments based on external economic factors, useful for multi-year contracts.
Question 4: A project manager discovers a potential conflict of interest when a team member evaluating proposals has a personal relationship with one of the vendors. What is the BEST course of action?
- Remove the team member from the evaluation process and document the action (Correct answer)
- Allow the evaluation to proceed since the relationship may not affect objectivity
- Ask the team member to recuse themselves voluntarily
- Cancel the current procurement and restart the process
Correct answer: Remove the team member from the evaluation process and document the action
Removing the team member from evaluation and documenting the conflict of interest protects procurement integrity and is the most direct corrective action.
Question 5: Which process involves tracking contract performance, making payments, and managing changes to ensure both buyer and seller meet obligations?
- Plan Procurement Management
- Conduct Procurements
- Control Procurements (Correct answer)
- Close Procurements
Correct answer: Control Procurements
Control Procurements monitors contract performance, processes payments, manages changes, and ensures both parties fulfill their obligations.
Question 6: A vendor claims they are entitled to additional payment because the project manager's instructions caused a delay. The vendor's claim is submitted in writing. This is known as:
- A change request
- A variance report
- A constructive change (Correct answer)
- A force majeure event
Correct answer: A constructive change
A constructive change occurs when buyer actions or instructions (even informal) cause the seller to perform work beyond the contract scope, entitling them to additional compensation.
Question 7: In an Agile procurement environment, which approach is MOST commonly used to engage vendors?
- Firm Fixed Price contracts with detailed SOW
- Time and Material contracts with defined sprints and outcomes (Correct answer)
- Cost Plus Percentage of Cost contracts
- Invitation for Bid with mandatory technical specifications
Correct answer: Time and Material contracts with defined sprints and outcomes
T&M contracts with sprint-based delivery align with Agile's iterative nature, providing flexibility while maintaining defined outcomes per iteration.
Which procurement document is MOST appropriate when the buyer wants vendors to propose innovative solutions?