PMP Managing Budget and Costs 5 — Questions and Answers
Question 1: A project has spent $400,000 to date with a CPI of 0.80. What was the Earned Value (EV)?
- $320,000 (Correct answer)
- $500,000
- $480,000
- $360,000
Correct answer: $320,000
CPI = EV / AC → 0.80 = EV / $400,000 → EV = $320,000.
Question 2: What is the key difference between contingency reserves and management reserves from a budget control perspective?
- Contingency reserves require sponsor approval to use; management reserves do not
- Contingency reserves are in the cost baseline; management reserves are not (Correct answer)
- Management reserves are for known risks; contingency reserves are for unknown risks
- Both types are included within the cost baseline
Correct answer: Contingency reserves are in the cost baseline; management reserves are not
Contingency reserves are part of the cost baseline for known risks, while management reserves sit outside the baseline for unknown unknowns.
Question 3: A project manager is conducting a cost-benefit analysis. The project costs $200,000 and delivers $350,000 in benefits. What is the benefit-cost ratio (BCR)?
- 0.57
- 1.75 (Correct answer)
- 1.50
- 2.00
Correct answer: 1.75
BCR = Benefits / Costs = $350,000 / $200,000 = 1.75, indicating the project delivers $1.75 in benefits for every $1 spent.
Question 4: Which funding limit reconciliation technique adjusts the schedule to accommodate periods when project funding will be constrained?
- Reserve analysis
- Cost aggregation
- Funding limit reconciliation (Correct answer)
- Parametric modeling
Correct answer: Funding limit reconciliation
Funding limit reconciliation aligns the planned spending profile with funding constraints, often requiring schedule adjustments.
Question 5: A project was originally budgeted at $1,000,000. After several approved scope changes, the budget increased to $1,200,000. The current approved budget is known as the:
- Original cost baseline
- Management reserve
- Budget at Completion (BAC) (Correct answer)
- Estimate at Completion (EAC)
Correct answer: Budget at Completion (BAC)
The BAC is the total authorized budget for the project, which is updated when approved scope changes alter the cost baseline.
Question 6: When should the project manager escalate a budget variance to senior management?
- After every status report cycle
- Only when the project is about to close
- When the variance exceeds the threshold defined in the cost management plan (Correct answer)
- When a team member requests it
Correct answer: When the variance exceeds the threshold defined in the cost management plan
The cost management plan defines escalation thresholds; variances beyond those levels require senior management notification and action.
Question 7: A risk that was not identified during planning occurs and consumes part of the project budget. Which budget component should be used to fund this unplanned event?
- Contingency reserves from the cost baseline
- Management reserves held above the cost baseline (Correct answer)
- The project's profit margin
- The sponsor's discretionary fund
Correct answer: Management reserves held above the cost baseline
Unknown unknowns (unidentified risks) are funded by management reserves, which exist outside the cost baseline specifically for this purpose.
A project has spent $400,000 to date with a CPI of 0.80.
What was the Earned Value (EV)?