PMP Compliance and Business Value 3 — Questions and Answers
Question 1: A project operating under an agile framework must still meet GDPR data privacy requirements. How should the team handle compliance in sprints?
- Address all compliance requirements in a dedicated compliance sprint at the end
- Embed compliance acceptance criteria into relevant user stories throughout the project (Correct answer)
- Assign a separate compliance team to handle all regulatory tasks independently
- Document compliance requirements in the project charter and revisit at project close
Correct answer: Embed compliance acceptance criteria into relevant user stories throughout the project
Embedding compliance criteria directly into user stories ensures regulatory requirements are met incrementally rather than deferred.
Question 2: What is the PRIMARY purpose of a compliance register in project management?
- Track team member training and certifications
- Document all applicable regulations, standards, and contractual obligations and their status (Correct answer)
- Record audit findings and corrective actions taken
- List all project risks related to non-compliance
Correct answer: Document all applicable regulations, standards, and contractual obligations and their status
A compliance register catalogs all applicable requirements and their current status to ensure nothing is overlooked.
Question 3: A project manager is asked to demonstrate business value to an executive steering committee mid-project. Which evidence is MOST compelling?
- A Gantt chart showing tasks completed on schedule
- A burn-down chart demonstrating sprint velocity
- Early benefit metrics showing progress toward strategic KPIs (Correct answer)
- A risk register with all high risks marked as mitigated
Correct answer: Early benefit metrics showing progress toward strategic KPIs
Executives care about strategic outcomes; early benefit metrics tied to KPIs directly demonstrate business value progress.
Question 4: Which of the following BEST describes the relationship between project governance and compliance?
- Governance establishes authority structures, while compliance ensures adherence to applicable rules within those structures (Correct answer)
- Governance and compliance are interchangeable terms in project management
- Compliance is a subset of risk management, separate from governance
- Governance only applies to external regulatory requirements, while compliance is internal
Correct answer: Governance establishes authority structures, while compliance ensures adherence to applicable rules within those structures
Governance defines the decision-making framework, and compliance ensures project activities conform to regulations, policies, and standards within that framework.
Question 5: A project manager learns that a recently passed regulation will require significant rework of a nearly complete deliverable. The BEST course of action is to:
- Deliver the original scope and let operations handle the regulatory change
- Raise a change request to incorporate the new regulatory requirement and update the business case (Correct answer)
- Ignore the regulation until it is formally enforced
- Escalate to legal and suspend all project activities
Correct answer: Raise a change request to incorporate the new regulatory requirement and update the business case
New regulations that affect project scope require a formal change request and business case update to remain compliant.
Question 6: An organization's project selection committee prioritizes projects based on Net Present Value (NPV). A project with a positive NPV but negative societal impact is proposed. How should the project manager advise?
- Approve the project since NPV is the defined selection criterion
- Reject the project because societal impact always outweighs financial metrics
- Flag the societal impact as a risk and include it in the business case for decision-maker review (Correct answer)
- Recommend replacing the NPV criterion with a balanced scorecard approach
Correct answer: Flag the societal impact as a risk and include it in the business case for decision-maker review
The project manager's role is to surface all material factors—including societal impact—so decision-makers have complete information.
Question 7: During project execution, a team member reports a potential ethics violation by a key vendor. The project manager should FIRST:
- Immediately terminate the vendor contract
- Document the report and investigate through the organization's established ethics process (Correct answer)
- Inform the client and let them decide how to proceed
- Ignore it if the vendor's deliverables are meeting quality standards
Correct answer: Document the report and investigate through the organization's established ethics process
Ethics violations must be handled through the organization's formal ethics process, starting with documentation and investigation.
A project operating under an agile framework must still meet GDPR data privacy requirements.
How should the team handle compliance in sprints?