  1. A project manager notices that defects are clustering around a single supplier's components. Which quality tool best visualizes the frequency distribution of defect categories to identify the dominant cause?

    Answer: Pareto chart

    A Pareto chart ranks defect categories by frequency, making it easy to identify the vital few causes responsible for most defects.

  2. During Manage Quality, the team performs a process audit and finds that approved procedures are not being followed. What is the MOST appropriate next step?

    Answer: Initiate a change request to address the process gap

    Manage Quality findings that reveal process non-conformance should be addressed through formal change requests to correct the quality system.

  3. A project team is using statistical sampling to inspect deliverables. What is the PRIMARY benefit of this approach over 100% inspection?

    Answer: It reduces inspection cost and time while providing statistical confidence

    Statistical sampling provides a cost-effective way to draw conclusions about an entire population without inspecting every unit.

  4. Which quality concept distinguishes between the cost of conformance and the cost of non-conformance?

    Answer: Cost of quality (COQ)

    Cost of quality (COQ) categorizes all quality-related spending into prevention/appraisal costs (conformance) and internal/external failure costs (non-conformance).

  5. A control chart shows eight consecutive data points on one side of the mean. What should the project manager conclude?

    Answer: A non-random pattern (rule of seven) indicates the process is out of control

    The rule of seven states that eight or more consecutive points on one side of the mean signal a non-random, assignable cause requiring investigation.

  6. In the PMBOK framework, which process is responsible for translating the quality management plan into executable quality activities?

    Answer: Manage Quality

    Manage Quality (formerly Perform Quality Assurance) converts quality planning into executable quality activities and audits.

  7. A project manager wants to determine whether a relationship exists between the number of test hours and the number of defects found. Which tool should be used?

    Answer: Scatter diagram

    A scatter diagram plots two variables against each other to determine whether a correlation or relationship exists between them.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Passing score, score release, exam format, retake policy, renewal, eligibility, time limit, exam information · verified Oct 2026
  2. pearsonvue.com — Test delivery · verified Oct 2026