Procurement Management Flashcards
7 cards from real PMP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 7 Procurement Management flashcards as text
Which contract type places the MOST financial risk on the buyer?
Answer: Cost Plus Percentage of Cost (CPPC)
CPPC gives the seller no incentive to control costs since their fee increases as costs rise, placing maximum risk on the buyer.
A seller delivers work that technically meets contract requirements but misses the project's intent. What should the project manager do FIRST?
Answer: Issue a change order to redefine requirements
A change order formalizes the adjustment to scope or requirements to align the deliverable with intent while keeping the contract valid.
What is the PRIMARY purpose of a bid conference (also called a bidders' conference)?
Answer: To ensure all prospective sellers have equal understanding of procurement requirements
Bidders' conferences give all prospective sellers the same information simultaneously to ensure fair and equal understanding of requirements.
Which document serves as the formal authorization from the buyer to the seller to begin work?
Answer: Notice to Proceed (NTP)
A Notice to Proceed (NTP) is the formal authorization that instructs the seller to begin work on the contract.
During contract negotiations, the seller insists on a higher price due to material cost increases. The buyer wants to maintain the original price. This is BEST described as:
Answer: A risk event that was not identified
Unidentified material cost increases represent a risk event that was not adequately identified and planned for in risk management.
A project manager is evaluating make-or-buy decisions. Which factor would MOST favor outsourcing to a vendor?
Answer: The work requires specialized expertise not available internally
Specialized expertise unavailable internally is a primary driver to outsource, as building that capability in-house would be costly and time-consuming.
In a Fixed-Price Incentive Fee contract, what happens if the final cost exceeds the Point of Total Assumption (PTA)?
Answer: The seller absorbs all additional costs above the PTA
Above the PTA, the seller bears 100% of additional costs, which effectively converts the contract to a firm-fixed-price arrangement.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Exam format, renewal, time limit, score validity, passing score, retake policy, score release, fees, exam information · verified Nov 2026
- pearsonvue.com — Test delivery · verified Nov 2026