  1. Which process focuses on improving team member competencies, interaction, and the overall team environment to enhance project performance?

    Answer: Develop Team

    Develop Team improves the competencies, team member interaction, and the overall team environment to enhance project performance.

  2. A project manager notices conflict between two senior engineers over technical approach. What is the MOST effective conflict resolution technique?

    Answer: Collaborating/problem solving

    Collaborating/problem solving addresses the root cause of conflict and finds a mutually acceptable solution, making it the most effective long-term technique.

  3. Tuckman's team development model stages in order are:

    Answer: Forming, Storming, Norming, Performing, Adjourning

    Tuckman's model progresses through Forming, Storming, Norming, Performing, and Adjourning as teams develop cohesion and effectiveness.

  4. Which type of power is MOST effective for a project manager who lacks formal authority?

    Answer: Expert power

    Expert power, derived from knowledge and skill, is highly effective for project managers who may lack formal organizational authority.

  5. A project manager wants to recognize individual team member achievements publicly. Which motivation theory BEST supports this approach?

    Answer: Maslow's hierarchy — esteem needs

    Public recognition addresses esteem needs in Maslow's hierarchy, including recognition, respect, and status among peers.

  6. Which document is used to formally assign a team member to a project and defines their roles and responsibilities?

    Answer: Project team assignments

    Project team assignments formally document the team members assigned to the project and their specific roles.