  1. Midway through a software development project, a project manager discovers that a key stakeholder from the finance department has not been identified. This stakeholder is now expressing significant concerns about the project's budget and potential impact on their department's resources. What is the project manager's most appropriate first step?

    Answer: Add the new stakeholder to the stakeholder register and perform a stakeholder analysis.

    The correct first step when a new stakeholder is identified is to add them to the stakeholder register. This official project document lists all identified stakeholders. Following this, a stakeholder analysis should be performed to understand their interests, influence, and expectations. This analysis is crucial before developing engagement strategies or updating other plans.

  2. A project manager is using a Power/Interest Grid to classify stakeholders for a large construction project. A stakeholder is assessed as having high power but low interest in the project's day-to-day activities. According to best practices, how should the project manager engage with this stakeholder?

    Answer: Keep Satisfied

    For stakeholders with high power and low interest, the appropriate strategy is to 'Keep Satisfied.' These stakeholders have the ability to significantly impact the project, but they don't need to be involved in every detail. The project manager should ensure their needs are met and they are satisfied with the project's progress without overwhelming them with information. 'Manage Closely' is for high power/high interest stakeholders. 'Keep Informed' is for low power/high interest, and 'Monitor' is for low power/low interest.

  3. Which of the following is a key output of the Plan Stakeholder Engagement process?

    Answer: Stakeholder Engagement Plan

    The Stakeholder Engagement Plan is the primary output of the Plan Stakeholder Engagement process. This plan outlines the strategies and actions required to effectively engage stakeholders throughout the project lifecycle based on their needs, expectations, interests, and potential impact. The Stakeholder Register is an input to this process. The Issue Log is used to track issues, and the Communications Management Plan, while related, is a separate plan focused on the mechanics of communication.

  4. During a project's execution phase, the project manager notices that a key stakeholder, who was previously supportive, has become resistant to the project's objectives. This is creating conflict within the project team and delaying decisions. What is the BEST course of action for the project manager to take?

    Answer: Refer to the stakeholder engagement plan to review the planned engagement strategy for this stakeholder and adjust as needed.

    The most appropriate action is to first consult the stakeholder engagement plan. This plan should contain strategies for engaging this stakeholder. The project manager should review the plan to understand the stakeholder's needs and motivations and then determine why their engagement level has changed. Based on this analysis, the plan can be adjusted. Escalating or using force should not be the first step, and simply documenting the issue without taking action is insufficient.

  5. A project manager is leading a project with a diverse group of stakeholders from different cultural backgrounds and with varying communication preferences. Some prefer detailed written reports, while others prefer informal, face-to-face updates. To ensure effective engagement, what should the project manager do?

    Answer: Tailor communication methods and styles to meet the individual needs and preferences of each stakeholder.

    Effective stakeholder engagement requires understanding and respecting the diverse needs and preferences of each stakeholder. A one-size-fits-all approach is ineffective. The project manager should tailor communication styles and methods to align with individual stakeholder preferences, which fosters better relationships and more productive engagement.

  6. Which of the following describes the desired engagement level for a stakeholder who is aware of the project and its potential impacts and is actively working to ensure the project is a success?

    Answer: Leading

    The 'Leading' engagement level describes a stakeholder who is actively engaged in ensuring the project's success. They are not just supportive but are taking a proactive role. 'Supportive' stakeholders are in favor of the project but may not be as actively involved as a 'Leading' stakeholder. 'Neutral' stakeholders are aware but neither support nor oppose, and 'Resistant' stakeholders are opposed to the project.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Exam format, renewal, time limit, score validity, passing score, retake policy, score release, fees, exam information · verified Nov 2026
  2. pearsonvue.com — Test delivery · verified Nov 2026