  1. A project requires a specialized component. The project manager needs to decide whether the team should develop the component internally or purchase it from an external vendor. The decision will be based on cost, the team's existing capacity and expertise, and the long-term strategic goals of the organization. What is this process called?

    Answer: Make-or-Buy Analysis

    Make-or-buy analysis is a technique used in the Plan Procurement Management process to determine whether a particular work product or service is best provided by the project team or procured from outside sources. It considers various factors like cost, resource availability, expertise, and strategic alignment to make an informed decision.

  2. A project has a well-defined scope, but the buyer wants to incentivize the seller to complete the work ahead of schedule. The buyer is willing to share a portion of the cost savings if the final costs are below the target but wants to cap the total project cost. Which contract type is most appropriate for this scenario?

    Answer: Fixed-Price Incentive Fee (FPIF)

    A Fixed-Price Incentive Fee (FPIF) contract is ideal here. The fixed-price component is suitable for the well-defined scope, while the incentive fee motivates the seller to improve performance, such as by finishing early or reducing costs. The contract includes a price ceiling, which caps the maximum cost the buyer will pay.

  3. A project manager for a government agency needs to procure a complex new software system. The requirements are high-level, and the agency wants to understand the range of possible solutions and technologies available in the market before defining detailed specifications. Which procurement document should be issued first?

    Answer: Request for Information (RFI)

    A Request for Information (RFI) is the appropriate document to use in this situation. An RFI is used to gather information about vendor capabilities and potential solutions when the requirements are not yet firm. It helps the buyer learn about the market before issuing a more formal Request for Proposal (RFP) or Request for Quotation (RFQ).

  4. During the execution of a project under a cost-reimbursable contract, the seller submits an invoice for materials that the project manager believes are not compliant with the specifications outlined in the procurement statement of work. The seller disagrees and demands payment. This disagreement is best described as a:

    Answer: Claim

    A claim is a formal request or demand by one party of a contract seeking compensation or other consideration from the other party for what is perceived as a change or breach of the agreement. In this case, the seller's demand for payment for disputed work constitutes a claim that must be managed through the claims administration process.

  5. A project team is evaluating proposals from several vendors for a critical project component. The procurement documents stated that technical capability and past performance are the most important evaluation factors. One vendor's proposal is significantly cheaper than the others but does not demonstrate the required technical expertise. What is the team's most appropriate action?

    Answer: Disqualify the vendor for failing to meet the mandatory technical criteria.

    Source selection criteria are established during procurement planning and must be followed to ensure a fair and transparent process. If a vendor fails to meet the minimum mandatory requirements, such as technical capability in this scenario, their proposal should be considered non-compliant and disqualified from further evaluation, regardless of price.

  6. In which type of contract does the buyer assume the highest level of cost risk, as the seller's profit increases directly with the project's costs?

    Answer: Cost Plus Percentage of Cost (CPPC)

    The Cost Plus Percentage of Cost (CPPC) contract places the maximum cost risk on the buyer. In this contract type, the seller is reimbursed for all allowable costs, and their fee is calculated as a percentage of those costs. This creates a negative incentive for the seller to control costs, as higher costs lead to a higher profit. Due to this high risk for the buyer, CPPC contracts are rarely used.

Written and edited by , founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Exam format, renewal, time limit, score validity, passing score, retake policy, score release, fees, exam information · verified Nov 2026
  2. pearsonvue.com — Test delivery · verified Nov 2026