Managing Budget and Costs Flashcards
6 cards from real PMP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Managing Budget and Costs flashcards as text
A project has a Cost Performance Index (CPI) of 0.85 and a Schedule Performance Index (SPI) of 1.05. Based on these metrics, what is the current status of the project?
Answer: The project is over budget and ahead of schedule.
A CPI less than 1.0 indicates that the project is over budget (costing more than planned for the work accomplished). [3, 9] An SPI greater than 1.0 indicates the project is ahead of schedule (accomplishing more work than planned for the time period). [4, 6] Therefore, a CPI of 0.85 and an SPI of 1.05 means the project is over budget and ahead of schedule.
A project manager is establishing the project budget. The sum of the cost estimates for the individual work packages is $500,000. Through risk analysis, the team identifies known risks and allocates an additional $50,000 to address them if they occur. This $550,000 total is then approved as the performance measurement baseline. What does the $50,000 represent?
Answer: Contingency Reserve
Contingency reserves are funds allocated for identified risks, or 'known-unknowns,' and are included within the cost baseline that the project manager controls. [8, 22, 27] Management reserves are for 'unknown-unknowns' (unidentified risks) and are not part of the cost baseline. The cost baseline itself is the total of work package estimates plus the contingency reserve.
A project has a Budget at Completion (BAC) of $300,000. At the current status check, the Earned Value (EV) is $120,000, and the Actual Cost (AC) is $150,000. The project manager believes the cost variances experienced so far are typical and will continue for the remainder of the project. What is the Estimate at Completion (EAC)?
Answer: $375,000
When current cost variances are expected to continue, the appropriate formula for Estimate at Completion (EAC) is BAC / CPI. [1, 17] First, calculate the Cost Performance Index (CPI): CPI = EV / AC = $120,000 / $150,000 = 0.8. [3, 5] Then, calculate the EAC: EAC = BAC / CPI = $300,000 / 0.8 = $375,000.
Which of the following is a key output of the Determine Budget process?
Answer: Cost Baseline
The primary output of the Determine Budget process is the Cost Baseline. [19, 32] This is the authorized, time-phased budget that will be used to measure, monitor, and control the project's cost performance. Cost Estimates and Basis of Estimates are inputs to this process, and Change Requests are typically an output of the Control Costs process.
A project is significantly over budget. The project sponsor wants to know the cost performance required for the remaining work to finish the project exactly on its original budget (BAC). Which metric should the project manager provide?
Answer: To-Complete Performance Index (TCPI)
The To-Complete Performance Index (TCPI) calculates the cost performance that must be achieved on the remaining work to meet a specific management goal, such as the original Budget at Completion (BAC). [2, 23, 31] It essentially answers the question, 'How efficiently must we use our remaining resources to meet the budget?'
A project manager is preparing a cost estimate for a new software development project. Due to the high level of uncertainty in the initial stages, the project manager uses the costs from a similar, completed project as a basis for the estimate. Which estimating technique is being used?
Answer: Analogous Estimating
Analogous estimating uses historical data and expert judgment from a similar past project to estimate costs for a current project. It is a form of expert judgment, is generally less costly and time-consuming than other techniques, but is also less accurate. It is most useful when there is limited detailed information about the current project.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Exam format, renewal, time limit, score validity, passing score, retake policy, score release, fees, exam information · verified Nov 2026
- pearsonvue.com — Test delivery · verified Nov 2026