Which process ensures that only approved changes are incorporated into the project baseline?
Answer: Perform Integrated Change Control
Perform Integrated Change Control reviews all change requests and approves or rejects modifications to baselines.
A project has a BAC of $500,000, an EV of $200,000, and an AC of $250,000. What is the Variance at Completion (VAC)?
Answer: -$125,000
EAC = BAC/CPI = $500,000/(200,000/250,000) = $625,000; VAC = BAC - EAC = $500,000 - $625,000 = -$125,000.
During project closure, the project manager should ensure which of the following is completed?
Answer: Lessons learned are documented and archived
Capturing and archiving lessons learned is a key closure activity that supports organizational learning and future projects.
What is the key difference between a project and a program?
Answer: A program is a group of related projects managed in a coordinated way to obtain benefits not available individually
Programs consist of related projects whose coordinated management delivers strategic benefits and control beyond managing them separately.
A project manager is managing stakeholder expectations when deliverable quality falls short. Which response is MOST appropriate?
Answer: Proactively communicate the issue, explain the impact, and present corrective options
Transparent, timely communication about quality issues with proposed solutions maintains stakeholder trust and enables collaborative problem-solving.
Which estimating technique produces the MOST accurate estimates and requires the MOST time and resources?
Answer: Bottom-Up Estimating
Bottom-up estimating breaks work into its smallest components and rolls up individual estimates, providing higher accuracy at the cost of more time and effort.
In a Kanban system, what is the primary purpose of setting Work in Progress (WIP) limits?
Answer: To limit the number of tasks in each workflow stage and expose bottlenecks
WIP limits reduce multitasking, improve flow efficiency, and make bottlenecks visible so the team can address them.
Written and edited by Nathan Beja, founder of Practice Test Geeks, with AI assistance. Exam facts are checked against the official sources linked below. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Exam format, renewal, time limit, score validity, passing score, retake policy, score release, fees, exam information · verified Nov 2026
- pearsonvue.com — Test delivery · verified Nov 2026