PMP Flashcards

7 cards from real PMP practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 PMP flashcards as text
  1. A project manager notices that a key stakeholder is consistently missing status meetings. What is the BEST first step?

    Answer: Update the communications management plan and reach out to understand their preferred communication method

    Adapting communication approaches to stakeholder preferences increases engagement and aligns with the communications management plan.

  2. Which process group involves defining project scope, creating the WBS, and establishing the project baseline?

    Answer: Planning

    The Planning process group is where scope is defined, the WBS is created, and baselines are established.

  3. A project is 60% complete and has a CPI of 0.85. What does this indicate?

    Answer: The project is over budget — spending more than planned per unit of work

    A CPI below 1.0 means costs are running higher than planned for the work accomplished.

  4. What is the PRIMARY purpose of a Risk Register?

    Answer: To record identified risks, their analysis, and planned responses

    The Risk Register captures identified risks, probability/impact assessments, and response strategies.

  5. A team member identifies a workaround during project execution. When is a workaround MOST appropriate?

    Answer: When an unplanned risk event occurs and no response plan exists

    Workarounds are unplanned responses developed to deal with risk events that had no prior response plan.

  6. In an agile project, the team's velocity is used primarily to:

    Answer: Forecast how much work can be completed in future sprints

    Velocity measures the average amount of work (story points) completed per sprint and is used for release planning forecasts.

  7. Which conflict resolution technique results in a temporary solution and often leads to recurring conflict?

    Answer: Withdraw/Avoid

    Withdraw/Avoid postpones conflict rather than resolving it, often allowing it to resurface later.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Passing score, score release, exam format, retake policy, renewal, eligibility, time limit, exam information · verified Oct 2026
  2. pearsonvue.com — Test delivery · verified Oct 2026