A project manager discovers mid-project that a regulatory agency has authority over the project's deliverables but was never listed in the stakeholder register. What is the BEST immediate action?
-
A
Ignore the agency since they weren't identified at project initiation
-
B
Add the regulatory agency to the stakeholder register and assess their influence
-
C
Escalate to the project sponsor to decide whether to acknowledge the agency
-
D
Delay the project until the agency formally requests involvement