PMI-RMP Risk Categorization and Risk Breakdown Structure 2 — Questions and Answers
Question 1: A project team reviews their Risk Breakdown Structure and finds that 80% of identified risks fall under the 'Organizational' category. What is the most appropriate conclusion?
- The project is performing well because technical risks are minimal
- The RBS categories need to be redefined to balance the distribution
- Internal organizational factors pose the greatest risk concentration for this project (Correct answer)
- Quantitative analysis should be skipped since risks are well-categorized
Correct answer: Internal organizational factors pose the greatest risk concentration for this project
A concentration of risks in one category signals that organizational factors represent the dominant source of uncertainty and should receive focused management attention.
Question 2: How does the Risk Breakdown Structure relate to the Work Breakdown Structure (WBS)?
- The RBS replaces the WBS in risk-intensive projects
- Both structures can be cross-referenced to identify which work packages carry the most risk (Correct answer)
- The RBS is derived directly from the WBS by adding risk attributes to each deliverable
- The WBS is a subset of the RBS and is used only for technical risks
Correct answer: Both structures can be cross-referenced to identify which work packages carry the most risk
Comparing the RBS with the WBS allows project teams to identify which work packages or deliverables are associated with the highest concentration of risks.
Question 3: Which risk category in a standard RBS would typically include risks arising from reliance on a single vendor for a critical component?
- Technical risks
- Project management risks
- External risks (Correct answer)
- Organizational risks
Correct answer: External risks
Vendor or supplier dependency is an external risk because it originates outside the project team and organization, typically classified under the 'External' RBS category.
Question 4: Risk categorization supports quantitative risk analysis primarily by doing which of the following?
- Providing probability values for each risk category automatically
- Grouping correlated risks to model their combined effect more accurately (Correct answer)
- Eliminating risks that cannot be quantified from the analysis
- Assigning risk owners based on financial expertise
Correct answer: Grouping correlated risks to model their combined effect more accurately
Grouping correlated risks by category allows analysts to model their combined effect in simulations like Monte Carlo, producing more accurate overall project risk exposure estimates.
Question 5: What is a 'risk meta-category' in the context of risk management?
- A risk that has been escalated to senior management for resolution
- A high-level grouping that contains multiple sub-categories of related risks (Correct answer)
- A category reserved exclusively for risks with very high probability
- A special register entry for risks that have already been realized
Correct answer: A high-level grouping that contains multiple sub-categories of related risks
A risk meta-category is a broad, high-level grouping in the RBS that contains multiple sub-categories; for example, 'Technical' may contain sub-categories like 'Requirements,' 'Technology,' and 'Performance.'
Question 6: How does using a pre-defined Risk Breakdown Structure improve the quality of risk identification workshops?
- It limits discussion to only pre-approved risk types, reducing meeting time
- It ensures participants are guided through all relevant risk areas systematically (Correct answer)
- It automatically scores each risk based on industry benchmarks
- It prevents participants from suggesting risks outside the project scope
Correct answer: It ensures participants are guided through all relevant risk areas systematically
A pre-defined RBS acts as a structured prompt during workshops, guiding participants to consider risks across all relevant categories and reducing the chance of missing significant risk areas.
Question 7: Which of the following risk sub-categories would most likely appear under a 'Project Management' top-level RBS category?
- Currency exchange rate fluctuations
- Estimating errors and schedule slippage (Correct answer)
- Regulatory and compliance changes
- Natural disasters affecting the project site
Correct answer: Estimating errors and schedule slippage
Estimating errors and schedule slippage are internal project management risks stemming from how the project is planned and controlled, which fall under the Project Management RBS category.
A project team reviews their Risk Breakdown Structure and finds that 80% of identified risks fall under the 'Organizational' category.
What is the most appropriate conclusion?