PMI-RMP Certification Risk Response Planning & Monitoring Flashcards

6 cards from real PMI-RMP Certification practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 PMI-RMP Certification Risk Response Planning & Monitoring flashcards as text
  1. What is the purpose of a risk trigger (also called a risk symptom or warning sign)?

    Answer: To indicate that a risk event is about to occur so a contingency plan can be activated

    Risk triggers are early warning indicators that signal a risk is imminent, allowing the team to activate contingency plans proactively.

  2. In risk monitoring, what does a 'risk audit' examine?

    Answer: The effectiveness of risk responses and the risk management process

    Risk audits assess whether risk responses are working as planned and whether the overall risk management process is being followed effectively.

  3. Which reserve is set aside to address known-unknown risks (identified risks with response plans)?

    Answer: Contingency Reserve

    Contingency reserves are budgeted funds planned to address specific identified risks if they occur, and they are part of the project cost baseline.

  4. What is the 'escalate' risk response strategy used for?

    Answer: Addressing risks that are outside the project team's authority or scope

    Escalation is used when a risk exceeds the project team's authority or spans organizational boundaries, requiring a higher-level decision-maker to own the response.

  5. A risk owner is primarily responsible for which activity?

    Answer: Implementing and monitoring the agreed risk response

    The risk owner is the individual assigned to carry out the agreed risk response plan and to monitor the risk throughout the project lifecycle.

  6. What is 'active acceptance' as a risk response strategy?

    Answer: Establishing a contingency reserve or plan without taking advance action to address the risk

    Active acceptance acknowledges the risk and establishes a contingency reserve or fallback plan while not taking proactive steps to reduce it beforehand.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. pmi.org — Test delivery, fees, renewal, score validity, passing score, score release, test dates, exam format, retake policy, exam information · verified Oct 2026