In agile projects, how should a Scrum Master handle a stakeholder who frequently interrupts the development team with direct requests?
-
A
Allow direct communication to keep stakeholders informed
-
B
Shield the team by routing requests through the Product Owner
-
C
Schedule a weekly meeting for the stakeholder to present all requests
-
D
Escalate the issue immediately to senior management