A project has a Budget at Completion (BAC) of $500,000.
After 60% of the work is completed, the Actual Cost (AC) is $350,000.

What is the Cost Performance Index (CPI)?

Select your answer

What Practice Test Geeks adds beyond an AI chat for PMBOK

An AI chatbot can quiz you, but it can't reproduce the exam conditions or keep your record. Here you get:

  • A timed, full-length PMBOK mock exam — 180 questions in 230 minutes with a 61% pass mark, modeled on the official exam's question count and time limit, followed by a score report broken down by exam domain.
  • A fixed PMBOK question bank: the same test every attempt, so your score is comparable from one try to the next instead of changing with every regenerated quiz.
  • Progress saved on your device: completed tests, scores and missed questions stay in My Progress, so you can retake only what you got wrong.
  • A printable PMBOK cheat sheet you can print or save as a PDF.
  • PMBOK flashcards built from the same question bank.
Start the Timed PMBOK Mock Exam →

These practice questions were written with AI tools. They are not real exam questions. We have not yet matched this exam's facts to an official source, so confirm fees, dates and rules with the exam body. Not reviewed by a subject-matter expert. Editorial policy