Question 1: A process log table shows Reactor A temperature readings at 6-hour intervals: 6am=310°F, 12pm=318°F, 6pm=325°F, 12am=312°F. What is the average temperature over the 24-hour period?
- 316.25°F (Correct answer)
- 325°F
- 315°F
- 318°F
Correct answer: 316.25°F
Average = (310 + 318 + 325 + 312) / 4 = 1265 / 4 = 316.25°F.
Question 2: A bar chart shows monthly chemical usage in gallons: Jan=4,200, Feb=3,800, Mar=4,500, Apr=4,100. Which month had the greatest increase compared to the previous month?
- March (Correct answer)
- February
- April
- January
Correct answer: March
March increased by 700 gallons over February, which is the largest single-month increase in the dataset.
Question 3: A trend line graph shows pressure rising from 50 psi at 8am to 80 psi at 2pm. If the trend is linear, what was the pressure at 11am?
- 65 psi (Correct answer)
- 60 psi
- 70 psi
- 75 psi
Correct answer: 65 psi
The pressure rises 30 psi over 6 hours (5 psi/hr), so at 11am (3 hours in) it is 50 + 15 = 65 psi.
Question 4: A table lists flow rates for three pumps: Pump 1=240 gpm, Pump 2=185 gpm, Pump 3=205 gpm. If Pump 2 fails, what percentage of total flow capacity is lost?
- 29.4% (Correct answer)
- 23.5%
- 33.3%
- 26.1%
Correct answer: 29.4%
Total capacity = 630 gpm; Pump 2 = 185 gpm; 185/630 × 100 ≈ 29.4%.
Question 5: A pie chart shows the composition of plant downtime: Equipment Failure 40%, Scheduled Maintenance 35%, Operator Error 15%, Other 10%. If total downtime was 200 hours, how many hours were due to scheduled maintenance?
- 70 hours (Correct answer)
- 80 hours
- 35 hours
- 65 hours
Correct answer: 70 hours
35% of 200 hours = 0.35 × 200 = 70 hours of scheduled maintenance.
Question 6: A graph displays two lines: Line A shows tank level rising at 2 feet/hour, starting at 4 feet. Line B shows tank level dropping at 1 foot/hour, starting at 10 feet. After how many hours do the lines intersect?
- 2 hours (Correct answer)
- 3 hours
- 4 hours
- 1 hour
Correct answer: 2 hours
Setting 4 + 2t = 10 − t gives 3t = 6, so t = 2 hours.
Question 7: A table records valve positions (% open) and corresponding flow rates. At 25% open: 120 gpm; at 50% open: 240 gpm; at 75% open: 360 gpm; at 100% open: 480 gpm. What type of relationship is this?
- Linear (Correct answer)
- Exponential
- Logarithmic
- Inverse
Correct answer: Linear
Each 25% increase in valve opening produces a constant 120 gpm increase in flow, indicating a linear relationship.
A process log table shows Reactor A temperature readings at 6-hour intervals: 6am=310°F, 12pm=318°F, 6pm=325°F, 12am=312°F.
What is the average temperature over the 24-hour period?