In a project control context, what is the primary purpose of a Variance at Completion (VAC)?
-
A
To measure the current cost efficiency of the project
-
B
To project the expected cost overrun or underrun at project completion
-
C
To determine the remaining budget available for future work
-
D
To calculate the schedule delay in monetary terms