PCC Cheat Sheet 2026

The 30 highest-yield PCC facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.

100 questions
180 min time limit
70.00% to pass
  1. Which decision-making technique is BEST suited when a group must reach consensus on a complex project controls problem with many variables? Nominal group technique
  2. In a structured problem-solving session, a team uses a cause-and-effect diagram. Which category would 'inadequate training' fall under? People
  3. Which risk response strategy involves shifting the negative impact of a risk to a third party? Transfer
  4. Which of the following metrics is classified as a lagging indicator in project performance measurement? Actual Cost (AC) spent to date
  5. In bottom-up estimating, costs are estimated at the work package level and then aggregated. What primary advantage does this provide over top-down methods? It produces higher accuracy because detailed scope is used as the basis
  6. A PMO implementing a governance framework should prioritize which element to ensure project controls adoption? Executive sponsorship and visible commitment
  7. In multi-project environments, which approach BEST prevents resource conflicts between projects competing for shared resources? Establish a centralized resource pool managed at the program or portfolio level
  8. During strategic planning, a PMO identifies that two approved projects compete for the same critical resource. The BEST initial action is to: Perform resource leveling and present trade-off options to leadership
  9. What is the role of mentoring in Project Controls Certification professional development? Guiding and supporting professional growth through experience sharing
  10. Which procurement document provides the most detailed technical and administrative requirements for a project? Statement of Work (SOW)
  11. Which technique is used to systematically identify and prioritize long-range uncertainties that could impact an organization's strategic plan? Scenario planning
  12. A risk response that involves changing the project plan to eliminate a threat entirely is called: Avoid
  13. Which document formally authorizes a contractor to proceed with work beyond the original contract scope? Change Order
  14. Which tool is commonly used for qualitative risk assessment? Risk matrix
  15. In project controls, a procurement baseline is used primarily to: Track vendor performance against contracted deliverables and costs
  16. Which of the following is a leading indicator that scope creep is occurring on a project? Increasing actual costs with no corresponding approved changes
  17. A project controller identifies that a subcontractor's actual costs have exceeded the contract value by 15%. The FIRST action should be to: Review the contract terms and determine if a formal change order is warranted
  18. What is the purpose of feedback in Project Controls Certification professional development? To provide constructive guidance for improvement
  19. What is the primary purpose of an independent project cost review (ICR) or independent cost estimate (ICE)? To provide an unbiased check of the project estimate for decision-making
  20. Which of the following is NOT a valid method for calculating Estimate at Completion (EAC) in EVM? EAC = EV / SPI
  21. Which project selection method assigns scores to projects based on how well they satisfy multiple strategic criteria and then ranks them by total score? Weighted scoring model
  22. During a Monte Carlo simulation for schedule risk analysis, which output is MOST useful for communicating schedule confidence levels to stakeholders? S-curve showing probability of completion by date
  23. Which cost control technique compares actual expenditures against a planned budget without considering the value of work actually completed? Simple cost variance tracking
  24. Which concept describes the informal power a project manager gains through expertise and knowledge? Expert power
  25. Which contract risk mitigation strategy involves the owner retaining a percentage of each payment until the project is substantially complete? Retainage
  26. A project controller reviewing contract terms notices the contract includes a liquidated damages clause. This clause is intended to: Compensate the owner for losses if the contractor misses key milestones
  27. A project report shows EAC = $1,200,000 and BAC = $1,000,000. What is the Variance at Completion (VAC)? -$200,000
  28. Which EVM technique credits earned value when a work package is exactly 50% complete upon start and 100% upon finish? 50/50 rule
  29. A pending change has not yet been approved but is expected to occur. How should it be reflected in the project budget? Tracked as a pending change in the budget at completion forecast
  30. An activity has an Early Start (ES) of Day 5 and a Late Start (LS) of Day 8. What is the total float? 3 days