PCC Performance Measurement & KPIs 2

Free ยท Instant Results

A project has a Budget at Completion (BAC) of $500,000, an Earned Value (EV) of $200,000, and an Actual Cost (AC) of $250,000. What is the Cost Performance Index (CPI)?