A project is behind schedule and over budget. The sponsor asks the team to fast-track. Which risk does this decision most likely introduce?
-
A
Increased rework due to overlapping activities
-
B
Reduced resource utilization
-
C
Lower project cost
-
D
Improved stakeholder satisfaction