A project faces a dispute over liquidated damages after a delay. The contractor argues force majeure; the owner argues poor planning. Which process BEST resolves this without litigation?
-
A
The owner unilaterally deducts LDs from payment
-
B
A Dispute Review Board (DRB) reviews contemporaneous records and issues a recommendation
-
C
The contractor halts work until the dispute is settled
-
D
Both parties ignore the clause and negotiate a final settlement verbally