A project controls manager discovers that the schedule baseline was set unrealistically by the client, causing ongoing disputes with the contractor. Which negotiation approach best addresses this structural conflict?
-
A
Ignore the baseline discrepancy and focus on current milestones
-
B
Conduct an interest-based negotiation to revise the baseline collaboratively
-
C
Escalate to legal counsel immediately
-
D
Issue a unilateral schedule update without client approval