A project is 30% over budget. A stakeholder asks for a briefing but has limited technical knowledge. The best approach is to:
-
A
Provide the full EVM technical report without simplification
-
B
Use plain language, visual charts, and focus on business impact and recovery plan
-
C
Refuse to discuss until the issue is resolved
-
D
Send only the raw data spreadsheet