A change order is being negotiated but work must proceed to avoid schedule delay. What mechanism allows work to start before final pricing is agreed?
-
A
Force account authorization
-
B
Unilateral change order
-
C
Letter of intent or undefinitized change order (UCO)
-
D
Provisional sum