A time-and-material (T&M) change order differs from a lump-sum change order primarily in that:
-
A
T&M requires a fixed price before work begins
-
B
T&M reimburses actual costs plus a fee, with scope risk borne by the owner
-
C
T&M transfers all risk to the contractor
-
D
T&M does not require documentation of labor hours