A project owner requests a scope addition after the baseline is set. What is the FIRST step the project controls team should take?
-
A
Issue a change order immediately
-
B
Evaluate the impact on cost, schedule, and risk
-
C
Reject the request until the project is complete
-
D
Update the WBS without formal documentation