  1. Which risk response strategy involves shifting the negative impact of a risk to a third party?

    Answer: Transfer

    Risk transfer moves the financial or operational consequence to another party, such as through insurance or fixed-price contracts.

  2. A project team identifies a risk with a 40% probability and a $500,000 impact. What is the risk's Expected Monetary Value (EMV)?

    Answer: $200,000

    EMV is calculated by multiplying probability (0.40) by impact ($500,000), yielding $200,000.

  3. What is the primary purpose of a risk register in project controls?

    Answer: Document identified risks and response plans

    A risk register is the central repository for all identified risks, their assessments, owners, and planned responses.

  4. In a tornado diagram, what does the length of each bar represent?

    Answer: The range of impact a variable has on the project outcome

    Each bar in a tornado diagram shows the swing — the difference between the high and low outcomes — for each risk variable.

  5. Which type of risk cannot be eliminated through diversification because it affects the entire market or industry?

    Answer: Systematic risk

    Systematic risk (also called non-diversifiable risk) arises from macroeconomic factors and affects all projects in a market.

  6. What is a 'residual risk' in the context of project risk management?

    Answer: The risk remaining after mitigation measures are applied

    Residual risk is the level of risk that persists after all planned risk responses have been implemented.

  7. During a quantitative risk analysis, which technique uses statistical sampling to model the probability of different outcomes?

    Answer: Monte Carlo Simulation

    Monte Carlo Simulation runs thousands of iterations using probability distributions to forecast a range of possible project outcomes.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. We have not yet matched this exam's facts to an official source, so confirm fees, dates and rules with the exam body. Not reviewed by a subject-matter expert. Editorial policy