PCC Contract Management & Procurement Flashcards

6 cards from real PCC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 6 PCC Contract Management & Procurement flashcards as text
  1. Which contract type places the most financial risk on the buyer?

    Answer: Cost-plus-fixed-fee

    Cost-plus contracts reimburse all allowable costs, so the buyer bears the risk if costs exceed estimates.

  2. In project controls, a procurement baseline is used primarily to:

    Answer: Track vendor performance against contracted deliverables and costs

    The procurement baseline measures actual vendor cost and schedule performance against what was contractually agreed.

  3. What document formally authorizes a seller to begin work on a contract?

    Answer: Notice to Proceed (NTP)

    A Notice to Proceed (NTP) is the official authorization issued to a contractor to begin work under the contract.

  4. Which procurement document provides the most detailed technical and administrative requirements for a project?

    Answer: Statement of Work (SOW)

    The Statement of Work (SOW) defines in detail the work to be performed, deliverables, schedule, and technical requirements.

  5. A project controller reviewing contract terms notices the contract includes a liquidated damages clause. This clause is intended to:

    Answer: Compensate the owner for losses if the contractor misses key milestones

    Liquidated damages are pre-agreed financial penalties assessed against the contractor for schedule delays that cause owner losses.

  6. In contract administration, a change order is best described as:

    Answer: A formal amendment modifying the contract scope, schedule, or cost

    A change order is a mutually agreed formal modification to the contract that adjusts scope, cost, or schedule.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. We have not yet matched this exam's facts to an official source, so confirm fees, dates and rules with the exam body. Not reviewed by a subject-matter expert. Editorial policy