  1. A project has BAC of $200,000, EV of $80,000, and AC of $100,000. Assuming current cost performance continues, what is the EAC?

    Answer: $250,000

    CPI = 80,000/100,000 = 0.8, so EAC = BAC/CPI = 200,000/0.8 = $250,000.

  2. In Agile consulting engagements, who is primarily responsible for prioritizing the product backlog?

    Answer: Product Owner

    The Product Owner orders the backlog to maximize value delivered to the client.

  3. What is the main purpose of a lessons-learned session at project closeout?

    Answer: To capture knowledge that improves future engagements

    Lessons learned document what worked and what didn't so future projects benefit from the experience.

  4. Which chart displays project activities as horizontal bars against a timeline?

    Answer: Gantt chart

    A Gantt chart shows activity start dates, durations, and end dates as bars on a calendar scale.

  5. Which item is typically considered a key component of the project baseline used for performance measurement?

    Answer: Scope, schedule, and cost baselines

    The performance measurement baseline integrates the approved scope, schedule, and cost baselines.

  6. A consultant reallocates staff so no one exceeds 40 hours per week, which extends the critical path. What technique was used?

    Answer: Resource leveling

    Resource leveling adjusts dates to address resource limits and can change the critical path, unlike smoothing.

  7. Which SMART criterion ensures a project objective has a defined deadline?

    Answer: Time-bound

    Time-bound means the objective includes a target date for completion.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. We have not yet matched this exam's facts to an official source, so confirm fees, dates and rules with the exam body. Not reviewed by a subject-matter expert. Editorial policy