In Earned Value Management (EVM), the Planned Value (PV) represents:
-
A
The authorized budget for work actually completed
-
B
The authorized budget for work scheduled to be completed by a given date
-
C
The actual cost incurred for work performed
-
D
The difference between budgeted and actual costs