  1. During a rough-in inspection, which measurement is the inspector most likely to verify for a toilet flange?

    Answer: Distance from the finished wall to the flange center

    Inspectors verify that the toilet flange center is 12 inches (or 10/14 inches for offset) from the finished wall to ensure proper toilet fit.

  2. Which test is required by most codes to verify the integrity of a DWV system before concealment?

    Answer: Water or air test per local code, typically at 10 feet of water head

    DWV systems are typically tested with water to a 10-foot head or with 5 psi air for a minimum of 15 minutes, per IPC/UPC requirements.

  3. An inspector finds that a horizontal drain pipe has zero slope over a 10-foot run. What is the correct action?

    Answer: Require rework to achieve the minimum ¼ inch per foot slope

    IPC and UPC require a minimum slope of ¼ inch per foot for drain pipes 3 inches and larger to ensure self-scouring flow.

  4. What is the primary purpose of a final plumbing inspection?

    Answer: To confirm all fixtures are installed, functional, and the system is leak-free

    The final inspection confirms that all fixtures are properly installed, all connections are watertight, and the system operates as designed.

  5. Which condition would cause an inspector to fail a water supply rough-in inspection?

    Answer: CPVC pipe installed without expansion joints on a long run in a hot environment

    CPVC and copper expand significantly with temperature changes; failing to allow for expansion on long runs can cause joint failures and leaks.

  6. When inspecting a water heater installation, which clearance is the inspector checking to prevent a fire hazard?

    Answer: Minimum 18-inch clearance from the floor for the ignition source in garages

    In garages, water heater ignition sources must be elevated at least 18 inches above the floor to reduce the risk of igniting fuel vapors.

  7. An inspector notices a P-trap arm that exceeds the maximum developed length before venting. What violation does this represent?

    Answer: Trap seal loss due to self-siphoning

    When a trap arm is too long, negative pressure from draining water can siphon the trap seal, allowing sewer gas into the building.