Tower Inspection Procedures Flashcards
6 cards from real PASMA practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Tower Inspection Procedures flashcards as text
What are the three occasions when a tower scaffold must be inspected under UK law?
Answer: Before first use, after any event affecting stability, and at intervals not exceeding 7 days
The Work at Height Regulations 2005, Schedule 6, requires inspection before first use on site, after any event that could affect stability (e.g., adverse weather, accidental impact), and at regular intervals not exceeding 7 days.
What is the first thing an inspector should check when inspecting a tower scaffold?
Answer: That the tower is erected on a firm, level base and the foundation is adequate
The foundation is the starting point for any inspection as everything above depends on it. The base must be on firm, level ground capable of supporting the total load. Adjustable legs or base plates should be properly set.
During an inspection, what should be checked about the guard rails?
Answer: That they are at the correct height (minimum 950mm), securely fixed, and free from defects
Guard rails must be at least 950mm above the platform, securely locked or clipped into position, and free from bends, cracks, or corrosion that could weaken them. An intermediate rail must also be fitted to reduce gaps to 470mm maximum.
What should an inspector do if they find a defect during a tower scaffold inspection?
Answer: Immediately take the tower out of service, report the defect, and ensure it is rectified before further use
Any defect that compromises safety must result in the tower being immediately taken out of service (e.g., with 'Do Not Use' signs). The defect must be reported and rectified by a competent person before the tower can be used again.
What information must be recorded on a tower scaffold inspection report?
Answer: The location, date, tower details, inspector name, results of the inspection, and any defects or actions required
A comprehensive inspection report must include the tower location, date and time of inspection, tower identification, name and signature of the competent inspector, detailed findings, any defects identified, and actions taken or required.
Who is responsible for ensuring that tower scaffold inspections are carried out on time?
Answer: The person or organisation controlling the work (usually the employer or principal contractor)
Under WAHR 2005, the duty to ensure inspections are carried out rests with the employer or the person controlling the work. On construction sites, this is typically the principal contractor or the employer of the tower users.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pasma.co.uk — Eligibility, exam dates, passing score, time limit, score validity, test delivery, fees, renewal, retake policy · verified Oct 2026