What must be included in the handover documentation for Part P notifiable work?
-
A
Electrical Installation Certificate (or MEIWC), schedules of test results and inspections, and Building Regulations compliance certificate or notification
-
B
Only a receipt for the work done
-
C
Only the consumer unit schedule
-
D
Only the test results without the certificate