You are managing a critical project with a tight deadline. Suddenly, a senior executive from another department assigns you an 'urgent' task that is unrelated to your project but has high visibility. This new task will consume a significant amount of your time. What is the most effective first step to take?
-
A
Immediately start working on the new task from the senior executive to show you are responsive and a team player.
-
B
Politely decline the task, explaining that your current project is the top priority and you have no time for other assignments.
-
C
Request a meeting with both your direct manager and the senior executive to discuss priorities and negotiate a realistic timeline for both tasks.
-
D
Delegate the new task to a junior team member so you can continue focusing on your critical project without delays.