A Scrum Master observes that the Developers are consistently being interrupted by stakeholders who ask for small, immediate changes directly. This is causing the team to lose focus on their Sprint Goal. Which of the following actions is the MOST appropriate for the Scrum Master to take?
-
A
Tell the Developers to ignore the stakeholders and focus only on the Sprint Backlog.
-
B
Coach the stakeholders on how their requests impact the team's focus and explain the proper way to introduce new work via the Product Owner.
-
C
Schedule a mandatory daily meeting for stakeholders to voice all their requests at once.
-
D
Act as a gatekeeper, personally fielding all stakeholder requests and deciding which ones to pass to the team.