During Sprint Planning, the Product Owner proposes a Sprint Goal. After discussion, the Developers believe they cannot complete all the selected Product Backlog Items to achieve the goal. According to the Scrum Guide, what is the primary accountability of the Developers in this situation?
-
A
To accept the Sprint Goal and work overtime to meet the Product Owner's expectations.
-
B
To negotiate with the Product Owner about the scope of the work for the Sprint, ensuring a realistic plan to achieve the Sprint Goal.
-
C
To ask the Scrum Master to cancel the Sprint since the goal is unachievable.
-
D
To begin the Sprint with the current plan and inform the Product Owner daily that the goal is at risk.