A Scrum Team is planning their work for a one-month Sprint. According to the Scrum Guide, what is the maximum amount of time the Sprint Planning event should take?
-
A
4 hours
-
B
As long as it takes for the team to feel comfortable
-
C
8 hours
-
D
2 hours per week of Sprint length