A project manager identifies a risk that could significantly delay the project. The team decides to change the project plan to eliminate the risk entirely by adopting a different technical approach that does not carry this risk. This is an example of which risk response strategy?
-
A
Mitigation
-
B
Avoidance
-
C
Transference
-
D
Acceptance