A project manager is overseeing the development of a new software application. During a team meeting, a developer suggests adding a new feature that was not in the original requirements, believing it will significantly impress the client. This addition is done without any formal change request or impact analysis on the schedule and budget. This is an example of:
-
A
Scope creep
-
B
Gold plating
-
C
Value engineering
-
D
Contingency planning