A project manager is analyzing a project's performance and calculates the Cost Performance Index (CPI) to be 0.85 and the Schedule Performance Index (SPI) to be 1.15. Which of the following statements BEST describes the project's current status?
-
A
The project is over budget and ahead of schedule.
-
B
The project is under budget and behind schedule.
-
C
The project is over budget and behind schedule.
-
D
The project is under budget and ahead of schedule.