A project is approaching the end of a major phase. According to the project governance plan, a formal review is required where key stakeholders and the sponsor will decide whether to provide additional funding and authorize the start of the next phase. This formal governance checkpoint is BEST known as a:
-
A
Sprint Retrospective
-
B
Phase Gate review
-
C
Project Kick-off Meeting
-
D
Lessons Learned Session