Project Management Practice Test

Project Management Earned Value Management (EVM) Questions and Answers

Free · Instant Results

A project has a Budget at Completion (BAC) of $150,000. At the current status date, the project has an Earned Value (EV) of $60,000 and an Actual Cost (AC) of $75,000. The project manager determines that the current cost variances are atypical and expects the remaining work to be completed at the budgeted rate. Which formula should be used to calculate the Estimate at Completion (EAC)?
▶ Start Practice Test