A project manager is using the Critical Path Method (CPM) for a complex construction project. Several concurrent paths are being analyzed. Which of the following statements BEST defines the critical path?
-
A
The shortest path through the network diagram, representing the quickest the project can be completed.
-
B
The path with the most critical and high-risk activities, regardless of its duration.
-
C
The longest path through the network diagram, which determines the shortest possible project duration.
-
D
The path that contains the most activities, indicating the highest complexity.