A Scrum Team has just completed a two-week sprint. During the Sprint Retrospective, the developers complain that the Product Owner was frequently unavailable, leading to significant delays in clarifying requirements. Which of the following is the MOST appropriate outcome for this ceremony?
-
A
The Scrum Master documents the issue and escalates it to the Product Owner's functional manager.
-
B
The team decides to extend the next sprint to four weeks to account for potential delays.
-
C
An action item is created for the Scrum Master and Product Owner to agree on specific, daily office hours for the PO to be available to the team.
-
D
The developers are told to make their best assumptions on requirements to avoid future delays.