A subcontractor on a fixed-price government contract is dissatisfied with a payment delay from the prime contractor. The subcontractor contacts the government's Contracting Officer directly to demand payment for services rendered. What is the Contracting Officer's most appropriate response based on the principle of privity of contract?
-
A
Pay the subcontractor directly and deduct the amount from the prime's next invoice.
-
B
Mediate the dispute between the prime contractor and the subcontractor.
-
C
Direct the subcontractor to resolve the issue directly with the prime contractor.
-
D
Initiate a termination for default against the prime contractor for failure to pay its subcontractor.