A government contracting officer issues a written notice to a contractor specifying a failure to make progress that endangers contract performance. The notice provides the contractor with 10 days to correct the issue. This type of notice is best described as a:
-
A
Show Cause Notice
-
B
Cure Notice
-
C
Letter of Concern
-
D
Stop-Work Order