An IT project manager is using the Critical Path Method (CPM) for scheduling. A delay on a specific task has occurred, but the overall project deadline has not been affected. How is this possible?
-
A
The project is using a phase-based Work Breakdown Structure.
-
B
The delayed task was not on the critical path and had sufficient float.
-
C
The project budget was increased to cover the delay.
-
D
The risk was previously identified in the risk register.